Back

Conditioning House Phase 4

Bradford
  • Sector Residential
  • Client Bradford Lofts LTD
  • Contract value £740,000
  • Duration 16 weeks
  • Status Completed

Description of works

We are adding an additional 13 apartments to this landmark building. A Unique and forward-thinking design.

Project Updates

  1. 1 year ago
    Site progress update, December 2023 – Conditioning House, Serviced Offices

    Progress update at our Serviced Office scheme at the Award – Winning Conditioning House, Bradford. We are converting this lower ground area into 10,000Sqft of luxury serviced office space with its own gym!

    All partition walls have been erected and the plasterboard has been fitted. Plastering is due to start next week along with the 1st fix wiring and piping.

  2. 2 years ago
    Site progress update, Decemeber 2022 – Conditioning House Phase 4

    We are well into the final stages at our Conditioning House Phase 4 project, on behalf of our clients Priestley Homes, we are delivering 13no. apartments under a JCT Design & Build contract.

    Kitchens are being fitted in all plots, with bathrooms no 80% complete with tiling progressing well. 2nd fix joinery has started this week as we to the finish line. Works are due to complete early 2023.

  3. 2 years ago
    Site progress update, November 2022 – Conditioning House Phase 4

    Works are flying on the fourth phase at Conditioning House.

    2nd side boarding is ongoing in Mill 2 with ceilings in two plots completed this week.

    Fire stopping is ongoing and complete in 2 plots so far. Plastering has now commenced as we hit the second half of the programme.

    Hot and cold feed completed to all plots with fire collars ongoing, electrical 1st fix is also completed to all plots.

    This week has seen the first kitchens being installed. We love seeing FF&E being installed and apartments coming to life.